We remove this value from the GUI and reports of calculations and replace it with other better defined values.
We should also review and correct out algorithms.
Table of Contents |
---|
Mockup - in order
Mockup | ||||
---|---|---|---|---|
|
Mockup - standalone calculator
...
The Abstract operations work time is a very abstract value and should not be show to the user in any scenario. Only the machine work time and labor work time make perfect sense for the user.
...
Operation dates - calculated from orders start dane
Operations start date = if
- has no children operations then
- Operations start date = Order start date
- else
- Operations start date = MAX(Next operation blocked to date calculated for children operations)
Operations duration time without nonworking time = Setup time + Additional time + if
...
Operation cycles on most used workstation = if
- not Divisible cycle time then
- + Cycle time * roundUp(Numer of cycles needed in order / Number of workstations)
- else
- + Cycle time * (Numer of cycles needed in order / Number of workstations)
Operations duration time without nonworking time = Setup time + Additional time + Cycle time * Operation cycles on most used workstation
Operations duration time = Operations duration time without nonworking time distributed across working time of shifts
...
- Next operation after type == Produced allOperation ended, then
- = Operations end date
- = Operations end date
- Next operation after type == Produced specified quantity, then
- = Operations start date + Next operations block duration
Next operation after cycles = if
- Next operation after produced quantity <= quantity of the operations main output product required in order
- = required number of cycles to
...
- produce Next operation after produced quantity
Next operation block duration without nonworking time = Operations start date + Setup time + if
- not else
- = required number of cycles to produce quantity of the operations main output product required in order
Next operation after cycles on most used workstation = if
- not Divisible cycle time then
- + Cycle time * = roundUp(Next operation after cycles / Number of workstations)
- else then
- + Cycle time * (= Next operation after cycles / Number of workstations)
Next operation block duration without nonworking time = Setup time + Additional time + Cycle time + Next operation after cycles on most used workstation
Next operation block duration = Next operation block duration without nonworking time distributed across working time of shifts
Order calculated end date = Operations end date of root operation
Operations duration distribution - from a given start date
Any type of duration time without nonworking time is independent from the time axis and does not take into account the the company is forking or not.
Only the duration time that takes this information into account is dependant from the operations starting date and the time axis context which indicated when the company is working or not.
Input data:
- Operations start date
- Operations duration time - or the Next operation block duration
- Operations end date - or the Next operations after block date
Gliffy | ||||
---|---|---|---|---|
|
Operations table in costs calculation
...