Operations duration time = Operations duration time without nonworking time distributed across working time of shifts

Operations end date = Operations start date + Operations duration time

Next operation after cycles = required number of cycles to produce Next operation after produced quantity

...

Next operations block duration = Next operations block duration without nonworking time distributed across working time of shifts
Next operations start date = Operations start date + Next operations block duration

Operations table in costs calculation

...