Next operation block duration = Next operation block duration without nonworking time distributed across working time of shifts
Operations duration distribution - from a given start date
Any type of duration time without nonworking time is independent from the time axis and does not take into account the the company is forking or not.
Only the duration time that takes this information into account is dependant from the operations starting date and the time axis context which indicated when the company is working or not.
Input data:
- Operations start date
- Operations duration time - or the Next operation block duration
Output data:
- Operations end date - or the Next operations after block date
Steps visualisation:
Operations table in costs calculation
...