Changes in CST 07, 08

Because the need occured to introduce two new parameters:

  • machine utilization time ratio 
  • labor utilization time ratio

it influences the cost calculation algorithm in CTS.

In particular, in all calculations of machine time and labor time (in CST 07, 08) should be modified algorithm of calculating the times:

Duration_of_operation = TPZ+Tj*n + Tadd (additional)

Machine_cost_of_operation = Duration_of_operation * machine_utilization_time_ratio

Labor_cost_of_operation = Duration_of_operation * labor_utilization_time_ratio_(FTE)